10MVA Transducer Successfully Put Into Operation in Tisco 450 m2 Sintering Machine2012-05-30

The remolding of Tisco triple-sinters main extraction fan transducer and its auxiliary projects conducted by DHC was completed at 5:20 pm on May 22nd, 2012, and it was put into trial run. On May 25th, 2012, two transducers successfully passed the 72-hour trial running test.
 

At present, the equipment is running in good condition and the energy saving is obvious; it can save more than 90 thousand electrical degrees per day with a power saving rate of above 20% which completely meets the project goals. For that, the iron works of Tisco veiled big red flowers over the transducers to express its satisfaction with DHC.
 

With the powerful technical strength and extensive field experience, DHC has successfully implemented a series of overall solutions for remolding large capacity synchronous machine with low voltage distribution, high voltage distribution, excitation and upper machine. The high voltage inverter was first applied to the 450㎡ sintering machine and has made its contribution to saving energy and reducing consumption in steel industry.

                                                                             DHC Site commissioning team

           

                                                                                Inverter with the big red flower

                                            Taiyuan iron and steel Engineering and technical personnel in debugging